Project Scope / Highlights

The temporary cooling provision is for Procuring, Installing and Operating Water Cooled Chilled Water Plant, Network, Power Generator Sets and associated works related to the Mall and three (3) adjacent buildings located within the Bawabat Al Sharq Development Project, in Baniyas East, Abu Dhabi, UAE. The project consists of deploying high efficiency packaged and mobile chiller plants which include water cooled chillers, packaged cooling towers, chilled water and condenser water pumps, make-up water tanks and pumps, side stream filtration system, diesel power generator sets, step up transformers, ring main, fuel tanks, controls, etc…. 24-Hour Operation and Maintenance teams are deployed to maintain proper cooling provision in an efficient and continuous manner.

Project

Bawabat Al Sharq Development Temporary Cooling Provision

Location

Baniyas – Abu Dhabi, UAE

Duration

April 12, 2011 – March 08, 2013

Consultant

Ian Banham & Associates

Contract Type

Rental Service

Plant Sizes

3,750 TR and 7 MVA power generators

Development / Client

Baniyas Investment & Development Company (BIDC), a majority owned subsidiary of the Baniyas Sports Club, in the areas of investment, development and management of real estate projects.

Project Gallery