Meraas is building Dubai Themed Parks where district cooling was the choice for supply air conditioning. Meraas as the developer and through its Employer’s Representative Samsung C&T awarded the infrastructure works to ARCO General Contracting. Samsung C&T have verified and instructed ARCO to award the chilled water network works to ADC. ADC will verify design and building the chilled water networks for Motion Gate and Lego Land in the vast project.
Project Scope / Highlights

Project
Chilled Water Network at Dubai Themed Parks (MERAAS)
Location
Dubai Themed Parks, Dubai – UAE
Duration
8 months
Consultant
AURECON, CLING
Contract Type
8 KM of secondary CHW Piping
Plant Sizes
6,000TR
Development / Client
Dubai Parks & Resorts
Dubai Parks and Resorts PJSC (DFM: DUBAIPARKS), will become the Middle East’s largest multi-themed leisure and entertainment destination comprising three separate theme parks and one water park: motiongate™ Dubai, a Hollywood movie inspired theme park concept; LEGOLAND® Dubai, the first LEGOLAND® theme park in the Middle East; LEGOLAND® Water Park; and Bollywood Parks™ Dubai, a first-of-its-kind entertainment destination that will showcase the authentic Bollywood movie experience.